Last updated: 6 Nov 2024 | 388 Views |
Build a warehouse to store products. Build a Happy Meebaan factory, strong, fast, Bang Khun Thian
HWHH 12x20 m., height 6.5 m., carpeted pile floor, 1 ton/sq m., price 3.16 million baht.
With a prefabricated warehouse system, walls and metal roof sheets, quick construction, engineering standards.
Used to build steel structures Ready-made warehouse system
The pillar structure is made of Wi-Frank steel. The roof frame is made of wei Frank steel.
Build time 120 days
Tel 0817052132 ID Line :@happymeebaan
ลิงค์ไลน์ >> https://lin.ee/hT7pyNU
เวบไซท์>> https://www.happy-warehouse.com/
ยูทูป >> https://www.youtube.com/c/Happymeebaan
เฟสบุ้ค >> https://www.facebook.com/happymeebaan.warehouse.home/
ติ๊กต๊อก >> https://www.tiktok.com/@happymeebaan?_t=8ZyzGSDLBmE&_r=1
Warehouse construction, factory construction, strong, fast, Bang Khun Thian Happy Meebaan
Warehouse construction, factory construction, with design, cheap, fast return on investment, strong, fast construction
HWHH 12x20 m., 6.5 m high, pile floor, carpet 1 ton/sq m, price 3.16 million baht
With prefabricated warehouse system, metal sheet walls and roof, fast construction, engineering standards
Using steel structure construction, prefabricated warehouse system
The column structure is a wi-flange steel Roof structure is steel wi-flange
Construction time 120 days
Call 0817052132 Louis Happy Mee Baan ID Line: @happymeebaan
Line link >> https://lin.ee/hT7pyNU
Website >> https://www.happy-warehouse.com/
YouTube >> https://www.youtube.com/c/Happymeebaan
Facebook >> https://www.facebook.com/happymeebaan.warehouse.home/
Tiktok >> https://www.tiktok.com/@happymeebaan?_t=8ZyzGSDLBmE&_r=1
Work details
Foundation work 14x20 m. Driven piles, excluding soil filling and area adjustment
1- Driven piles 22 deep, blow count distance 20-24 meters with footings According to the number of structural column points
2-Ground beam, size 20x50 cm around the building
3-Concrete work on piles, 22 Blow Conut distances, floor bearing capacity 1 ton/sq m, concrete thickness 15 cm, wire mesh 6 mm@20
Structural work, prefabricated building HWH 12x20 m., height 6.5 meters
Specifications
1- WF 200x100 steel columns, Happy standard wire gables, painted black or blue, column distance according to 3D model
2- 0.4 mm thick metal sheet roof, yellow Blue Scope with PE heat shield, thickness 5 mm, clip-lock roof system to prevent leakage
Rust-free galvanized roof purlin, Omega, thickness 2.0 mm, 1 meter ad distance with click-lock transparent roof, 2 column sections
3- 0.4 mm thick metal sheet wall, yellow Blue Scope, 1 meter brickwork Galvanized Omega wall panel, 0.8 mm thick
1 meter purlin spacing
4- Aluzinc ventilation flakes, 1.0 meters high, according to 3D model
5- 12x6 meter door awning, 5x3 meter
6- Leave the door work
7- Install J Bolt
Leave the door work, windows, brickwork, all work, the customer will do it himself
10-year structural warranty, 3-year roof leakage, 1-year other
Excluding land adjustment and filling work, excluding foundation work, piles, all concrete, excluding office work
Excluding bathroom work, excluding room partition work, excluding electrical and water systems, excluding various public drainage works
Use the customer's area for camping and use the water and electricity that the customer has prepared.
Foundation work installment
Installment 1 When signing the construction contract, pay 30%
Installment 2 When the pile is complete, pay 20%
Installment 3 When the ground beam is complete, pay 20%
Installment 4 Before pouring the floor (Let the customer check the steel) Pay 20%
Installment 5 When the floor pouring is complete, pay 10%
Installment 1: Deposit for production of parts, pay 30%
Installment 2: When the columns and roof structure are delivered, pay 20%
Installment 3: When the structure is installed, pay 25%
Installment 4: When the remaining materials (more than 90%) are delivered (metal sheets, purlins, walls, roofs), pay 15%
Installment 5: When the work is delivered, pay 10%
Start from designing the building to meet the customer's needs. The warehouse has no central column.
It will be of maximum use, strong, beautiful, and meet engineering standards.
Therefore, we end with the Happy Warehouse HWH steel warehouse structure as shown in this format.
Then design the foundation. By using carpet piles, since this area is a soft soil area, we must be very careful.
In terms of pile driving, we use I22 piles to drive according to the positions designed by the engineer, along with making footings.
Pillars, ground beams, tie 2 layers of floor steel, make drop footings, pour 15 cm thick concrete, and you will get carpet piles.
Load capacity 1 ton/sq m.
When the foundation is made, we will produce the parts at Happy Warehouse's factory and transport the parts.
The parts produced will be sent to the work site to install the warehouse with a prefabricated system, allowing us to install the warehouse quickly and strongly.
Starting with installing the warehouse columns, installing the gable, installing the wall purlins, installing the roof purlins, and installing the roof.
Then we will install the metal sheet walls, ventilation grilles, bricks, and melsheet awnings according to the design.
With this, we can deliver the warehouse project to the customer for use within the specified time.
Within 120-150 days
This one takes 150 days to install the entire building structure. Then the work can be delivered.
The advantages of building a factory, building a warehouse, building a warehouse, a prefabricated warehouse system, a warehouse for rent project
Happy Warehouse
are as follows:
1. We have experience in warehouse construction, building more than 200 projects.
2. We have more than 10 years of experience in warehouse construction, building factories.
3. We are a manufacturing factory, so we can control the quality more than the on-site construction system.
The size of the work and have direct experience in building prefabricated buildings, building warehouses, building factories
4. We accept construction contracts for the entire system from designing the work, building foundations to the
Building, building warehouses, building factories and architecture
5. The quotation is issued from the center using a material calculation program based on reality.
Reliable, not overcharging
6. Build warehouses, build factories, we guarantee leakage for 1 year and guarantee the structure for 10 years
7. Fast and accurate price quotation, the only company that can offer prices in just
5 minutes
8. Our roof structure and purlins use galvanized steel, making them rust-resistant and long-lasting
Strength 3500 KSC
9. Our roof is a clip-lock system, so there is no bolt shooting from the roof, reducing the risk of
roof leaks
10. Customers make a contract directly with the manufacturer, giving customers confidence in the guarantee
and money is not lost, not through middlemen
Call 0817052132 Louis Happy Meebaan ID Line: @happymeebaan
Line link >> https://lin.ee/hT7pyNU
Website